[Q32-Q53] Updated PRINCE2-Foundation Dumps PDF - PRINCE2-Foundation Real Valid Brain Dumps With 340 Questions!

Share

Updated PRINCE2-Foundation Dumps PDF - PRINCE2-Foundation Real Valid Brain Dumps With 340 Questions!

100% Free PRINCE2-Foundation Exam Dumps Use Real PRINCE2 Certification Dumps


PRINCE2 Foundation Exam is the entry-level certification in the PRINCE2 qualification scheme, and passing PRINCE2-Foundation exam is a prerequisite for taking the higher-level PRINCE2 Practitioner Exam. PRINCE2-Foundation exam consists of 60 multiple-choice questions, and candidates have one hour to complete it. The passing score for the exam is 55%, and successful candidates receive a globally recognized PRINCE2 Foundation certification.


PRINCE2-Foundation: PRINCE2 Foundation Professional salary

The average salary of a PRINCE2-Foundation: PRINCE2 Foundation exam certified expert in:

  • Europe - 49,000 EURO
  • United States - 65,000 USD
  • India - 6,70,000 INR
  • England - 38,500 POUNDS

 

NEW QUESTION # 32
What theme estimates the cost of delivering the project?

  • A. Progress
  • B. Change
  • C. Business Case
  • D. Plans

Answer: D


NEW QUESTION # 33
When are tolerances for a Work Package agreed?

  • A. As work on each product within the Work Package begins
  • B. When acceptinga Work Package
  • C. Once ail products have been developed and approved
  • D. When the Stage Plan is authorized by the Project Board

Answer: B


NEW QUESTION # 34
Which is a responsibility of a risk owner?

  • A. Manage, monitor and control all aspects of an assigned risk
  • B. Identify risks to the project that might occur in their department
  • C. Determine project risk appetite
  • D. Own and authorize the use of the risk budget to fund risk responses

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 35
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by stages
  • B. Manage by exception
  • C. Learn from experience
  • D. Continued business justification

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-plans.php


NEW QUESTION # 36
Which is one of the six aspects of project performance that needs to be managed?

  • A. Risk
  • B. Progress
  • C. Change
  • D. Security

Answer: A

Explanation:
Section: Volume A
Explanation


NEW QUESTION # 37
Which characteristic distinguishes a project from regular business operations?

  • A. Produces benefits
  • B. Incurs cost
  • C. Manages stakeholders
  • D. Introduces business change

Answer: D


NEW QUESTION # 38
Which risk response type is appropriate to respond to an opportunity?

  • A. Accept
  • B. Exploit
  • C. Transfer
  • D. Fallback

Answer: B

Explanation:
Section: Volume B
Explanation


NEW QUESTION # 39
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  • A. Pay for the project
  • B. Provide the resources and skills to deliver the desired result
  • C. Specify the benefits of the project
  • D. Specify the desired result

Answer: B


NEW QUESTION # 40
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

  • A. Defined roles and responsibilities
  • B. Manage by exception
  • C. Learn from experience
  • D. Tailor to suit the project environment

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.wrike.com/blog/project-management-basics-prince2-explained/


NEW QUESTION # 41
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement

  • A. 1 and 2
  • B. 3 and 4
  • C. 1 and 4
  • D. 2 and 3

Answer: A,D


NEW QUESTION # 42
Which is a purpose of the 'controlling a stage' process?

  • A. To update a project plan to incorporate the actuals from a stage plan
  • B. To produce a team plan for the work to be assigned to a team manager
  • C. To select and implement actions that will resolve deviations from a plan within tolerance
  • D. To obtain approvals for products delivered in a work package

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Controlling_a_Stage#Purpose


NEW QUESTION # 43
Which statement applies to Stage Plans?

  • A. Provide a baseline against which the Project Board monitor overall progress
  • B. Are produced at the same time as the Project Initiation Documentation
  • C. Assist the Project Manager in the day-to-day running and control of the project
  • D. Always have the same duration as the Project Plan

Answer: C


NEW QUESTION # 44
In what product should the quality criteria for a specialist product be recorded?

  • A. Project Product Description
  • B. Product Description
  • C. Quality Register
  • D. Quality Management Strategy

Answer: B


NEW QUESTION # 45
Which is a purpose of a Project Brief?

  • A. Describe the reporting requirements of the various layers of management involved with the project
  • B. Enable the assembly of the project mandate
  • C. Describe how changes to products will be controlled
  • D. Provide a solid basis for the initiation of the project

Answer: D


NEW QUESTION # 46
What is the change authority role permitted to authorize?

  • A. Risks to the project
  • B. Changes to stage tolerance
  • C. Changes to the project that do not exceed a defined budget
  • D. Adjustments to the limits on the change budget

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 47
Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?

  • A. Those that have been completed, but have NOT been quality checked
  • B. Those that have been broken down into sub-products
  • C. Those dependent on more than one other product
  • D. Those to be created outside the scope of the project

Answer: D


NEW QUESTION # 48
Which is a purpose of the 'controlling a stage' process?

  • A. To update a project plan to incorporate the actuals from a stage plan
  • B. To produce a team plan for the work to be assigned to a team manager
  • C. To select and implement actions that will resolve deviations from a plan within tolerance
  • D. To obtain approvals for products delivered in a work package

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Controlling_a_Stage#Purpose


NEW QUESTION # 49
Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the scope, timing and ownership of the benefit reviews required
  • B. Define the period over which the cost-benefit analysis will be based
  • C. Describe how to measure the performance of the project's products in operational use
  • D. Describe how to measure and confirm any benefits that are to be realised after the project is closed

Answer: B


NEW QUESTION # 50
Which of the following is NOT part of quality planning?

  • A. Agree acceptance criteria
  • B. Set quality tolerances
  • C. Gain acceptance of the project product
  • D. Define quality responsibilities

Answer: C


NEW QUESTION # 51
Which is a type of issue?

  • A. A lesson
  • B. An Exception Report
  • C. A risk with an estimated high impact
  • D. A request for change

Answer: D

Explanation:
Section: Volume A


NEW QUESTION # 52
What process aims to ensure accurate progress information is provided to the Project Manager?

  • A. Directing a Project
  • B. Managing Product Delivery
  • C. Starting up a Project
  • D. Managing a Stage Boundary

Answer: B


NEW QUESTION # 53
......


The EXIN PR2F exam is a foundation-level exam that assesses the candidate's knowledge of project management principles, as outlined in the PRINCE2 methodology. PRINCE2 - acronym for Projects IN Controlled Environments - originated in the UK and is now a globally recognized project management framework. The PR2F exam is specially designed for professionals who want to establish a career in project management or upskill their existing project management knowledge.

 

Pass Your PRINCE2-Foundation Exam Easily With 100% Exam Passing Guarantee: https://www.passcollection.com/PRINCE2-Foundation_real-exams.html

PRINCE2-Foundation Dumps are Available for Instant Access: https://drive.google.com/open?id=1Qyq9FlZyoqqVGSO7JDyiD2Gl7isjErju