New 2022 Guaranteed Success with PassCollection AACE-PSP Dumps AACE International PDF Questions [Q70-Q85]

Share

New 2022 Guaranteed Success with PassCollection AACE-PSP Dumps AACE International PDF Questions

Exceptional Practice To Planning & Scheduling Professional (PSP) Exam Pass the First Time


Planning & Scheduling Professional (PSP) Exam Certification Path

The certification path for the Planning & Scheduling Professional (PSP) Exam consists only of this Planning & Scheduling Professional (PSP) Examination. The applicants must fulfill the eligibility criteria of having at least 8 years of industry experience only or 4 years of industry experience plus 4 years of a related degree from a college.

 

NEW QUESTION 70
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

  • A. Start-no-later constraint on the first activity
  • B. Finish-no-earlier constraint on the first activity
  • C. Finish-no-later constraint on the last activity
  • D. Finish-no-earlier constraint on the last activity

Answer: C

 

NEW QUESTION 71
How many work days does it take to move the product from testing to sale?

  • A. 100.
  • B. 90.
  • C. 60.
  • D. 70.

Answer: A

 

NEW QUESTION 72
Identify the minimum project duration.

  • A. 21 months.
  • B. 20 months.
  • C. 19 months.
  • D. 16 months.

Answer: B

 

NEW QUESTION 73
Constraints control events or activities that __________________.

  • A. Affect only the backward pass.
  • B. Affect only the forward pass.
  • C. May be over-ridden by activity logic.
  • D. Are not based on project relationships.

Answer: C

 

NEW QUESTION 74
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities occur in series with a 15-day lag.
  • B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • C. The activities run concurrently.
  • D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

Answer: A

 

NEW QUESTION 75
Determine the correct formula and date for the late finish for Activity 2001.

  • A. LS.2002 + 1 day -> 08-30-01.
  • B. LS.2002 - 1 day -> 08-28-01.
  • C. LF.2001 - 1 day -> 08-28-01.
  • D. LS.2002- 1 day-> 08-29-01.

Answer: B

 

NEW QUESTION 76
An early start constraint dictates

  • A. The actual start of an activity.
  • B. The planned start of an activity.
  • C. The planned start of a successor activity
  • D. An activity's remaining duration.

Answer: C

 

NEW QUESTION 77
Which of the following is NOT true?

  • A. Constraints can interfere with the longest path calculation.
  • B. A network must contain only one Critical Path.
  • C. Multiple calendars can affect the total float calculation.
  • D. Remaining durations can exceed original durations.

Answer: D

 

NEW QUESTION 78
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-04-02.
  • B. 06-11-02.
  • C. 06-05-02.
  • D. 06-18-02.

Answer: C

 

NEW QUESTION 79
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. 2.
  • B. Does not change.
  • C. 1.
  • D. 3.

Answer: B

 

NEW QUESTION 80
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Expedite packaging by 5 days.
  • B. Delay manufacturing by 5 days.
  • C. Delay product release by 5 days.
  • D. Expedite printing by 5 days.

Answer: C

 

NEW QUESTION 81
What method offers the best chance of the schedule being used effectively to implement the project in the field?

  • A. Issue detailed schedule updates as frequently as possible.
  • B. Obtain consent and agreement to the schedule from the key project personnel.
  • C. Allow large time contingencies on milestones and completion deadlines.
  • D. Include detailed and stringent set of scheduling specifications in the contract.

Answer: B

 

NEW QUESTION 82
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

  • A. 2003 and 7001.
  • B. 2004.
  • C. 4001, 5001 and 6001.
  • D. 4001 and 5001.

Answer: D

 

NEW QUESTION 83
What is the workweek period for this project?

  • A. Sunday through Saturday
  • B. Sunday through Friday
  • C. Monday through Friday
  • D. Monday through Saturday

Answer: A

 

NEW QUESTION 84
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  • A. Not suitable for projects with long durations.
  • B. Not suitable for complicated projects with multiple planned critical paths.
  • C. Accuracy is increased by inserting delaying events into the as-planned schedule.
  • D. Less accurate as the analysis advances through the project.

Answer: C

 

NEW QUESTION 85
......


How to book the Planning & Scheduling Professional (PSP) Exam

Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:

  • Step 1: Visit the AACE’s website by clicking here
  • Step 2: Create a new account or log in to an existing account
  • Step 3: Select your professional exam
  • Step 4: Complete the required course and take PSP practice test
  • Step 5: Fill the application and submit all required documents
  • Step 6: Schedule your exam by following the instructions on the website

 

AACE-PSP EXAM DUMPS WITH GUARANTEED SUCCESS: https://www.passcollection.com/AACE-PSP_real-exams.html

Best Quality AACE International AACE-PSP Exam Questions: https://drive.google.com/open?id=1aJLmpdempbBCTGakp7gbPH9WQxyi1k_L