ISTQB ATM (ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]) Certification Exam is an advanced-level certification for professionals in the field of software testing. ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] certification is intended for individuals who have a thorough understanding of the software testing methodologies, including test planning, design, execution, and reporting. ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] certification builds upon the foundational knowledge provided by the ISTQB Certified Tester Foundation Level (CTFL) certification and the ISTQB Certified Tester Advanced Level - Test Analyst (CTAL-TA) certification.
NEW QUESTION # 30
Assume you are managing a test automation project for a mission-critical system.
Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework.
Which of the following management issues associated to the development of this custom automation framework is least likely to manage?
- A. The custom automation framework will require an adequate documentation
- B. The changes to the custom automation framework should be communicated to all external users of this tool under the GNU license
- C. Proper testing for the custom automation framework must be performed
- D. The custom automation framework will need proper maintenance
Answer: B
Explanation:
Section: Test Tools and Automation
Explanation/Reference:
NEW QUESTION # 31
In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.
You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.
Some requirements will most likely be completed too late to allow a proper test preparation.
You and your test team have already worked on several similar past projects in the same organization.
Which one of the following options would you expect to be the most effective at mitigating this risk?
- A. Make reasonable assumptions about the missing details and design lightweight tests that can be easily updated during test execution
- B. Don't prepare any test and just run the regression test suite to check that the new features don't introduce regression
- C. Don't design any test until the test execution starts, then communicate that test execution is blocked due to incomplete requirements
- D. Even if there are only few details missing, escalate the risk to the project manager without preparing any tests
Answer: A
Explanation:
Section: Test Management
Explanation/Reference:
NEW QUESTION # 32
You are the Test Manager of a new project that will have three formal levels of testing unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing and reactive testing strategies.
Which of the following answers describes the most consistent example of implementation of this test strategy during the execution of the system tests?
- A. Your test team executes scripted tests designed and implemented before the execution of the system test phase, to cover the identified product risks. It also performs exploratory testing sessions throughout the system test phase
- B. Your test team autonomously performs some exploratory testing sessions and, at the very end of the system testing phase, it also executes more system tests under the guidance of a sample of users
- C. Your test team executes system tests under the guidance of a sample of users throughout the system test phase
- D. Your test team executes exploratory tests following a session-based test management approach throughout the system test phase
Answer: A
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 33
Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?
- A. Mature organizations address product quality risks associated to non-functional characteristics only during the system test phase
- B. Mature organizations are aware that risk management of product quality risks only occurs during testing
- C. Mature organizations are aware that the contribution of testing to analysis of product quality risks is very important. The analysis should occur throughout the entire lifecycle
- D. Mature organizations don't waste time identifying the sources of risks. They only focus on identifying product quality risks
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 34
Your test team consists of four members (Mary, Bob, Mark, Dave) with different
interpersonal skills.
The following skills assessment spreadsheet shows the characteristics of the team
members with respect to a list of interpersonal-skills (for each characteristic only the
member with the highest level of that characteristic is indicated and marked with 'X'):
On the next project a member of your test team will have to perform some routine tasks
requiring collaboration with other teams.
Who in your test team would you expect to be most suitable at doing these tasks?
K4 3 credits
- A. Mark
- B. Mary
- C. Dave
- D. Bob
Answer: B
NEW QUESTION # 35
Which of the following statements about the TMMi test process improvement model is true?
K2 1 credit
- A. TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model
- B. In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level
- C. At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging
- D. TMMi has a staged architecture for process improvement with seven maturity levels
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 36
Assume you have some data related to confirmation testing during system testing of a past project.
In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.
You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.
Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
- A. 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
- B. 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
- C. 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of external failure
- D. 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of detection
Answer: A
Explanation:
Section: Test Management
Explanation/Reference:
NEW QUESTION # 37
Which one of the following metrics to be produced needs traceability between the test cases and each item in a proper test basis?
- A. Requirements coverage
- B. Mean time between failures for the system
- C. Trends in the lag time from defect reporting to resolution
- D. Cumulative number of reported defects versus cumulative number of resolved defects
Answer: A
Explanation:
Section: Test Management
Explanation/Reference:
NEW QUESTION # 38
You are the Test Manager of a new project that will have three formal levels of testinG.
unit, integration and system testing. The testing strategy you decide to adopt a blend of
risk-based testing and reactive testing strategies.
Which of the following answers describes the most consistent example of implementation
of this test strategy during the execution of the system tests?
K2 1 credit
- A. Your test team executes system tests under the guidance of a sample of users
throughout the system test phase - B. Your test team executes exploratory tests following a session-based test management
approach throughout the system test phase - C. Your test team executes scripted tests designed and implemented before the execution
of the system test phase, to cover the identified product risks. It also performs exploratory
testing sessions throughout the system test phase - D. Your test team autonomously performs some exploratory testing sessions and, at the
very end of the system testing phase, it also executes more system tests under the
guidance of a sample of users
Answer: C
NEW QUESTION # 39
The main objectives the senior management team wants to achieve are:
- to reduce the costs associated with dynamic testing
- to use reviews to ensure that the project is on course for success and following the plan
- to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles
- to determine the effectiveness of reviews in terms of phase containment
- to improve phase containment effectiveness
Which of the following answers would you expect to describe the best way to achieve these objectives?
- A. You should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the phase in which they have been introduced
- B. You should plan for formal exit-phase reviews at the end of each development phase and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the people responsible for those bugs
- C. You should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects
- D. You should plan for lightweight exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects
Answer: A
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 40
Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?
- A. Mature organizations address product quality risks associated to non-functional characteristics only during the system test phase
- B. Mature organizations are aware that risk management of product quality risks only occurs during testing
- C. Mature organizations are aware that the contribution of testing to analysis of product quality risks is very important. The analysis should occur throughout the entire lifecycle
- D. Mature organizations don't waste time identifying the sources of risks. They only focus on identifying product quality risks
Answer: C
Explanation:
Section: Test Management
Explanation/Reference:
NEW QUESTION # 41
Which of the following information would you expect to be the most useful to perform a defect clustering analysis?
- A. The trend in the lag time from defect reporting to resolution
- B. The defect removal efficiency information
- C. The defect component information
- D. The lifecycle phase in which the defect has been introduced
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 42
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
- A. Supporting the customer in the execution of acceptance testing
- B. Developing unit tests
- C. Executing unit tests
- D. Planning and executing tests during the integration test phase to detect interface defects
Answer: A
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 43
Assume you are managing the system testing phase of a project.
The system test execution period is scheduled to twenty weeks.
All tests are manual tests. You are following a risk-driven test approach.
During the last staff meeting the project manager tells you new deadlines that will not allow
completion of all the system tests.
Which of the following would you expect to be the best way to respond to this situation?
K2 1 credit
- A. No action is needed, test as much as possible in the remaining time period
- B. Automate all remaining tests
- C. Remove testers from your test team, so that they can be assigned to other projects
- D. Prioritize executing the tests for the highest product risks and track these risks
Answer: D
NEW QUESTION # 44
Which of the following would you expect to be most likely an example of a demotivating factor for testers?
- A. Test quality is measured by counting the number of customer/user reported problems.
- B. The testers are assessed on whether and how often they detect important and critical failures
- C. The management asks the testers to be kept informed about the intensity, quality and results of testing
- D. The same regressions tests are manually executed by the same testers, for every product release, without regression test tools
- E. The testers' recommendations to improve the system or its testability are adopted by the development team
Answer: A,D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 45
Consider the following statements describing the importance of improving the test process:
I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi Which of the following answers is correct?
- A. I., II. and III are true; IV. is false
- B. I., II., III. and IV are false
- C. I. and IV. are true; II. and III. are false
- D. I., II. and III. are false; IV. is true
Answer: B
Explanation:
Section: Improving the Testing Process
Explanation/Reference:
NEW QUESTION # 46
Which of the following statements describing the consequences of specifying test conditions at a detailed level is NOT true?
- A. For system testing, the specification of test conditions at a detailed level, carried out early in the project as soon as the test basis is established, can contribute to defect prevention
- B. The specification of test conditions at a detailed level can require the implementation of an adequate level of formality across the team
- C. In an environment where the test basis is continuously changing, it is recommended to specify test conditions at a detailed level in order to achieve a better maintainability
- D. The specification of test conditions at a detailed level can be effective when no formal requirements or other development work products are available
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 47
After a selection process you have selected a test management tool that is going be
introduced in your organization and used by your test team in a pilot project.
You have already identified the member of your test team who will be the administrator of
the tool, since he/she has a significant experience with the administration of test
management tools and so he/she is able to make effective and efficient up-front decisions
about "how" the tool will be used. You have also developed a training plan for the other
members of your test team.
In collaboration with the administrator of the tool you have also devised standard ways of
managing, storing and maintaining the tool and its assets including backup/restore
procedures.
You have also analyzed standard formats supported by the tool (CSV, XLS, XML, etc.) to
export, import and archive all the information managed by the tool itself (requirements, test
case specifications, test plans etc.) for compliance with the most important test
management tools, in order to minimize the impacts of migrating this information to a new
tool that could replace the existing one in the future.
Which of the following phases in the lifecycle of the new tool has NOT been adequately
considered in this description?
K2 1 credit
- A. Retirement
- B. Support and maintenance
- C. Acquisition
- D. Evolution
Answer: D
NEW QUESTION # 48
You are the Test Manager of a project that adopts a V-model with four formal levels of testinG. unit, integration, system and acceptance testing.
On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing.
Assume that no requirements defects have been reported after the release of the product.
Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?
- A. Time to conduct the requirements review
- B. Total number of defects attributable to requirements found during unit, integration, system and acceptance testing
- C. Number of defects found during the requirements review
- D. Total number of defects attributable to requirements, found during functional specification review, high- level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
- E. Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
Answer: C,D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 49
Assume that the following test cases have been executed at the end of the first week of
test execution: TC-001, TC-002 and TC-007. All these tests are 'passes'.
What is the MINIMUM number of the remaining test cases that must be successfully
executed to fulfill the EX1 exit criteria?
K3 2 credits
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION # 50
You are managing the system testing for a SOA based system. The integrated system
consists of several subsystems:
- A SOA middleware
- A CRM (Customer Relationship Management) system
- A BRM (Billing and Revenue Management) system
- A SMS (Subscriber Management System) system and you performed a risk analysis
based on these subsystems.
At the end of the scheduled period for test execution you produce a first classical report
based on the traditional metrics of testing. Test pass/fail status and bug status
(open/resolved) That table provides you a distorted picture of the quality risk, because
there is no indication of the risk level of the failed tests, the tests not run, or the open bugs.
Thus, you produce the following table to solve this distortion issue:
In the table above, where you have introduced the concept of risk weighting, the highest
risk test or bug report has a score of 1, while the lowest risk test or bug report has a score
of 0.04.
Which of the following subsystems, based on the risk scores of the table, is most risky?
K4 3 credits
- A. BRM
- B. SMS
- C. SOA
- D. CRM
Answer: D
NEW QUESTION # 51
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C- compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?
- A. Does the tool have a good general usability?
- B. Is the installation procedure of the tool easy?
- C. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-
178B standard? - D. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?
- E. Does the tool require a system with more than 4GB of RAM memory?
- F. What are the costs to qualify the tool as a verification tool under the DO-178B?
Answer: C,D,F
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 52
In the test strategy document your organization declares:
- To adopt a V-model development lifecycle, with three formal levels of testing unit, integration and system testing
- To use a blended risk-based and regression-averse testing strategy for each level of testing The following is an excerpt of the "approach" section for the system test plan document of a new project:
"Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.
Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected)." In the system test plan, no deviations from the test strategy are described.
Based only on the given information, which of the following statements is true?
- A. The approach described in the system test plan document is consistent with the risk-based testing strategy, but it is inconsistent with the regression testing strategy
- B. The approach described in the system test plan document is consistent with the test strategy
- C. The approach described the system test plan document is inconsistent with both the risk-based and regression testing strategies
- D. The approach described in the system test plan document is consistent with the regression testing strategy, but it is inconsistent with the risk-based testing strategy
Answer: C
Explanation:
Section: Test Management
Explanation:
NEW QUESTION # 53
......
ISTQB ATM Exam covers a broad range of topics related to test management, including test planning and control, test analysis and design, test implementation and execution, and test monitoring and reporting. ATM exam also covers topics such as risk management, configuration management, and test tools and automation. The syllabus is designed to provide a comprehensive understanding of the testing process and its management, and to equip test managers with the skills and knowledge needed to manage testing effectively.
Preparation Tools for ISTQB Advanced Test Manager Certification
Applicants will become ATM certified if they use verified materials and enroll in accredited training classes offered by ISTQB training partners. Therefore, examinees can choose from the following prep options:
- Sample Questions and Answers by ISTQB
The vendor offers comprehensive questions that follow the exam structure and contain detailed explanations. These sample questions help the candidates check their preparedness level and understand whether they have some gaps in their knowledge or not. Also, by answering questions similar to those in the real test, the candidates will find out which topics they need to focus on more. In addition, they can check if their judgment is correct by taking a look at the provided answers. So, if you are interested in getting those practice items, check out the official ISTQB ATM page and download them for free.
- ISTQB Advanced Test Manager Training Provided by Planit Testing
The Planit Testing is one of the accredited providers that ISTQB has to organize training classes for this Advanced Test Manager certification. This training is dedicated to experienced testers who are looking to become eligible for a test management role and get the necessary experience to leverage their career. Also, it focuses on test managers who want to accredit their expertise and get the necessary skills that will help them gain their employers, peers, and clients’ appreciation. Test leaders and managers are also targeted by this validation. They will find the ISTQB ATM useful for them as it helps them improve their test management abilities. To add more, the course has different objectives that follow the test structure. Therefore, the attendees will learn how to implement the goals, testing processes, and mission for managing a testing project. Also, they will know how to lead and organize risk identification as well as analysis sessions and use the results they obtain to improve productivity. What is more, the exam-takers will detail how to implement and create test plans and stay consistent with the test strategies and organizational policies. The candidates will also be taught how to come with a business case proposal for test activities so that they can outline the expected benefits and costs. If the test-takers choose this training option, they can enroll in the online self-study session for a fee of $750, which means that they can study at their pace and save their progress. What is peculiar is that this type of training offers a pass guarantee. This means that if the student doesn’t pass the certification exam, he/she can attend the training one more time over the course of 6 months without paying any extra costs. Still, this option doesn’t include the test re-sits. Besides, such training includes exam revision assistance, which means that the candidates have the opportunity to pass the final ATM test from the first time by having access to live revision sessions, online tutorials, and exam revision questions. Finally, applicants will have 6 months of access to the online course with the three-month extension being only $150.
- Guide to the ISTQB Certification as an Advanced Test Manager
This book can be bought from Amazon in the paperback or Kindle versions. Its author is Rex Black and it was developed for test managers to help them understand how they can gain the necessary skills to be an effective test manager. Therefore, it includes information about test planning, test estimation, test control, and test monitoring. The readers will also understand what they need to do to define the overall testing strategies and goals when they test different systems. Furthermore, such a guide offers applicants a hands-on opportunity to understand how to schedule, plan, and track this type of knowledge scope. Thus, when you finish reading this manual, you will be able to select, assign, and acquire the proper resources for different testing tasks and know how to organize, form, and lead different testing teams.
ATM Questions - Truly Beneficial For Your ISTQB Exam: https://www.passcollection.com/ATM_real-exams.html
Pass Exam Questions Efficiently With ATM Questions: https://drive.google.com/open?id=1evbhlLMFiXPHs73VrAs_hRXNjoXDoTKj