NEW QUESTION 109
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The 'classroom-based training materials' will be used as the basis for developing the 'e-learning course'. As a result, the executive wants to ensure that the 'classroom-based training materials' are of the required standard.
The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?

  • A. No, because the senior user should be responsible for specifying the quality criteria for the training materials.
  • B. Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
  • C. Yes, because the executive should be available to provide ad hoc direction to the project manager.
  • D. No, because the project manager should be given authority to manage the project on a day-to-day basis.

Answer: D

 

NEW QUESTION 110
While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log.
Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?

  • A. The Project Brief is a complex document and may not be approved by the Executive.
  • B. MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.
  • C. There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.

Answer: C

 

NEW QUESTION 111
One of the senior managers of the company that is developing the 'e-learning course' has worked with ABC Company before. The team manager for the delivery of the 'e-learning course' has looked on ABC Company's intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.
Is this an appropriate application of the 'learn from experience' principle, and why?

  • A. No, because the senior manager should advise the team manager of any lessons.
  • B. Yes, because the team manager should actively look for useful information.
  • C. Yes, because the project involves more than one organization.
  • D. No, because every project is unique and should deliver specific business objectives

Answer: B

Explanation:
Explanation/Reference:
Testlet 1
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term

A promotional calendar as a free Christmas gift - would target current and prospective customers and

the benefits would last into a second year
A series of television and press advertisements was too expensive

A direct mail shot to all customers - benefit would be short term

Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

 

NEW QUESTION 112
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
At the end of stage 2, the specialist 'e-learning course' supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier's standards and techniques.
Is this appropriate, and why?

  • A. Yes, because the quality management approach should take into account the supplier's standards, tools and techniques.
  • B. No, because the quality management approach should be created during the initiation stage and updated later.
  • C. No, because the quality management approach should be limited to ABC Company's quality standards.
  • D. Yes, because the product description for each product will define the required quality approach within each stage.

Answer: A

 

NEW QUESTION 113
Which of the following principles describes this statement?
"xxx defines tolerances for each project objective to establish limits of delegated authority"

  • A. Focus on products
  • B. Learn from experience
  • C. Manage by stages
  • D. Manage by exception

Answer: D

Explanation:
Explanation/Reference:
Question Set 1

 

NEW QUESTION 114
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for
this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are
being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago
the professional photographer produced the photo session schedule based on the operational staff schedule.
The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the E500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Plan prerequisites section?

  • A. Add 'Engineering team must be made available for photos'.
  • B. Add 'Compliance with the Data Protection Act'.
  • C. Delete entry 4 because the customer list is a deliverable of stage 2, not a prerequisite for stage 3.
  • D. Delete entry 2 because these are project benefits not prerequisites of the stage.
  • E. Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a prerequisite for stage
    3.

Answer: C,D

 

NEW QUESTION 115
HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:

Answer:

Explanation:

 

NEW QUESTION 116
The Health and Safety Training Project has been divided into four stages. The executive considers this project to be a compulsory project and has advised the project manager that it is not necessary to produce the project initiation documentation. This would mean that the project would consist of three delivery stages.
How well does this apply the 'manage by stages' principle?

  • A. It applies it poorly, because solid foundations should be established for every project.
  • B. It applies it poorly, because the stages should be shorter to provide more control to the project board.
  • C. It applies it well, because the justification for delivering the project is already understood.
  • D. It applies it well, because the project management method should be tailored to the project.

Answer: A

Explanation:
Explanation

 

NEW QUESTION 117
Scenario
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago.
She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed Executive for this project?

  • A. Add 'Director of Finance' because she understands the operation of the Information Technology Division and the Facilities Division.
  • B. Replace with 'Payroll Manager' because he is a very experienced and efficient qualified accountant.
  • C. Retain because he accepts that outsourcing is the best solution.
  • D. Retain because he has the right level of authority to be able to control the strategic nature of the Outsourcing project.
  • E. Replace with 'Director of Finance Division' because she can ensure a cost-conscious approach to the project that gives value for money.

Answer: D,E

 

NEW QUESTION 118
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him.
They promote existing training courses to other training companies and existing customers.
End of the additional information.
A construction company that is one of ABC Company's key clients has agreed to provide a member of the staff to review and comment on the 'e-learning course'.
Which stakeholder interest should the member of staff represent, and why?

  • A. Supplier, because this stakeholder provides the expertise required by the project.
  • B. User, because this stakeholder may train its staff using the 'e-learning course'.
  • C. User, because this stakeholder ensures that the project provides value for money.
  • D. Supplier, because this stakeholder is an external supplier.

Answer: C

 

NEW QUESTION 119
The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the 'e-learning course' incrementally. The project manager has asked the program manager how often the highlight reports are required, and what format the reports should be presented in.
Is this an appropriate approach to controlling progress, and why?

  • A. Yes, because the project event-driven controls need to align to program controls.
  • B. Yes, because the approach should support the delivery approach selected by the program.
  • C. No, because the progress controls should be documented in the project initiation documentation.
  • D. No, because the program team should review project progress using peer reviews.

Answer: C

Explanation:
Explanation/Reference:
Starting up and Initiating a Project
Testlet 1
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

 

NEW QUESTION 120
Drop down the right answer from Column 1 to column 2.

Answer:

Explanation:

Explanation

 

NEW QUESTION 121
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Introduction section?

  • A. No change to entry 1 because this shows the purpose and content of this document.
  • B. Amend entry 1 to read 'This document contains the controls and reporting to be established for the project management team'.
  • C. Amend entry 1 to read 'This document contains the means and frequency of communication between the project management team, the print company and other external parties.

Answer: A

Explanation:
Explanation/Reference:

 

NEW QUESTION 122
The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?

  • A. No, because it is the configuration item record of the relevant product description that is updated, not the work package.
  • B. No, because the work package should be checked to confirm the reporting arrangements of the 'e- learning course'.
  • C. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
  • D. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.

Answer: C

 

NEW QUESTION 123
Which of the following statements would NOT be included in the Project Product Description?

  • A. Project level tolerances
  • B. Composition
  • C. Purpose of the product
  • D. Quality criteria

Answer: D

 

NEW QUESTION 124
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer system?

  • A. Back-up of data must be kept until the data is no longer needed.
  • B. Planned periods of shutdowns of the computer system must be kept to a minimum.
  • C. Must be subject to regular back-ups.
  • D. No (zero) loss of system functionality.

Answer: D

 

NEW QUESTION 125
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
● Do nothing.
● Re-engineer selected business functions.
● Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
● A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
● Use PRINCE2.
● Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Reasons heading?

  • A. The Ministry of Food Hygiene (MFH) needs to deal with the increasing pressure to cut costs and better manage supplier's performance.
  • B. Relocating staff to the selected service provider's premises will mean that no property transfer is required.
  • C. Providing re-engineered services in-house will remove the need to transfer staff to a service provider.
  • D. The lack of up-to-date technology in MFH means a re-engineering of existing services will not necessarily deliver the performance improvements required.
  • E. The inadequate controls, outdated standards and outdated technology must be addressed.

Answer: A,B

Explanation:
Explanation/Reference:
http://www.whatisprince2.net/prince2-theme-business-case.php

 

NEW QUESTION 126
Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?

  • A. Amend entry 4 to 'The transferred products relating to the services provided by the Facilities Division'.
  • B. Delete entry 3 because this interface will be contained in the project control section of the Project Initiation Documentation.
  • C. Add 'Project Board, with responsibility for communicating progress to corporate management' to
  • D. Add 'Facilities Team Manager, with responsibility for the transfer of services provided by the Facilities Division' to Development Interfaces.
  • E. Delete entry 2 because this interface will be contained in the Communication Management Strategy.
  • F. Operations and maintenance Interfaces.

Answer: C,D

 

NEW QUESTION 127
MANAGING A STAGE BOUNDARY
The ABC Company trainers have been accredited and the course booking procedures have been amended.
The 'managing a stage boundary' process is taking place at the end of stage 3.
Which activity should occur during the 'update the business case' activity?

  • A. Review whether a new team manager should be appointed to lead the delivery of the pilot courses during
    stage 4.
  • B. Break the 'planned pilot courses' down into component products in order to identify the work required to
    deliver them.
  • C. Update the overall plan with the time and cost taken to develop the 'e-learning course' and 'amended
    course booking procedures'
  • D. Review whether the possible sales of the training course to external companies are likely to cover the
    project costs.

Answer: C

 

NEW QUESTION 128
Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this
project?

  • A. He is not appropriate for the role of Executive or Senior User.
  • B. He is responsible for the organization's procurement activates.
  • C. He was an engineer and worked in that area before taking up his current position.
  • D. He is responsible for the performance of supplier contracts.
  • E. He can influence the external supplier's Business Case.

Answer: B,D

 

NEW QUESTION 129
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar.
It has yet to be decided which of the photographers to use.
Which 2 statements explain why the Sales Manager should be appointed as User Assurance for this project?

  • A. He can provide an evaluation of the potential impact the calendar will have on sales.
  • B. He would like to move into the Marketing department in the future and sees this as an opportunity to work closely with the Marketing Director.
  • C. He can resolve any conflict in requirements between the Sales department and the Marketing department.
  • D. He joined the company last year with huge enthusiasm and is keen to increase sales.
  • E. He is able to advise on suitable stakeholder engagement of current and prospective customers.

Answer: A,E

 

NEW QUESTION 130
......


PRINCE2-Practitioner Exam Certification Path

You may be having some questions regarding how you can buy our PRINCE2 dumps, we are providing a flexible option of making payment using PayPal where you can make payment using a credit card. If you are purchasing from a country like India, then you can visit their website for more information about that payment details. Being a customer, if you are having any queries or looking for bulk purchase or additional discount, then feel free to drop us an email at [info@PassCollection](mailto:info@PassCollection).

What about once you are done with the purchase, do not worry, our services never use to get stop only after selling one product to you, we provide after-sales services as well like you will always get updated PRINCE2-Practitioner dumps in your profile because we use review PRINCE2-Practitioner exam dumps and get them updated regularly. you are getting multiple options to access our provided dumps first one is accessing it through an online exam simulator where you can practice all the questions and answer, which provide a lot of insights like about how you are performing, how much you had scored in your given attempt, what is the correct answer with a clear explanation of every question, you can find all these benefits from our provided online exam simulator. The second option to access our purchased dumps is using mobile applications, we already have a mobile application that you can download from the AppStore, play store, etc. and just log in with your username and password after that you are good and start using our mobile-friendly app. Anytime, if you feel that you need to have some support from our team, you can reach out to us by simply dropping an email, we will connect to you back on priority because we believe in providing customer service and satisfaction.

 

Powerful PRINCE2-Practitioner PDF Dumps for PRINCE2-Practitioner Questions: https://www.passcollection.com/PRINCE2-Practitioner_real-exams.html

2022 Realistic PRINCE2-Practitioner Dumps Exam Tips Test Pdf Exam Material: https://drive.google.com/open?id=17SsUhxoLkCuuPrzFZbpA2F_jD5liEMeJ