NEW QUESTION # 46
Where does a Buyer create a Scheduling Agreement release?

  • A. SAP Ariba Buying
  • B. SAP Business Network
  • C. SAP ERP system
  • D. SAP Integrated Business Planning (IBP)

Answer: C


NEW QUESTION # 47
When can a supplier create an Advanced Ship Notice in the Supplier Managed Inventory process using planned shipment?

  • A. After the goods receipt has been generated or updated
  • B. After manufacturing visibility has been sent to SAP Business Network
  • C. After the order confirmation has been sent to SAP Business Network
  • D. After the schedule line has been sent to SAP Business Network

Answer: D


NEW QUESTION # 48
What options does a supplier have in the supplier managed inventory process?
Note: There are 2 correct answers to this question.

  • A. Planned Shipment
  • B. Replenishment Order
  • C. Manufacturing Visibility
  • D. Forecast

Answer: A,B


NEW QUESTION # 49
What is the correct transaction sequence for Forecasting?

  • A. 1. Supplier Review, Commit and Submit 2. Buyer Review Commitments 3. Buyer Forecast Data Extraction & Transmission
  • B. 1. Buyer Forecast Data Extraction & Transmission 2. Buyer Review Commitments 3. Supplier Review, Commit and Submit
  • C. 1. Buyer Forecast Data Extraction & Transmission 2. Supplier Review, Commit and Submit 3. Buyer Review Commitments
  • D. 1. Buyer Review Commitments 2. Supplier Review, Commit and Submit 3. Buyer Forecast Data Extraction & Transmission

Answer: B


NEW QUESTION # 50
Regarding Scheduling Agreement Collaboration, in which planning horizon zone are suppliers allowed to create a ship notice?

  • A. Trade-off Zone
  • B. Firm Zone
  • C. Committed Zone
  • D. Planning Zone

Answer: B


NEW QUESTION # 51
Which of the following are possible time bucket views in SAP Business Network? Note: There are 2 correct answers to this question.

  • A. Daily
  • B. Weekly
  • C. Biweekly
  • D. Hourly

Answer: A,D


NEW QUESTION # 52
Which document can a supplier create for a return purchase order?

  • A. Order confirmation
  • B. Credit memo
  • C. Return Delivery
  • D. ASN

Answer: B


NEW QUESTION # 53
Which of the following items are recorded on an Inspection Lot?
Note: There are 2 correct answers to this question.

  • A. Customer Complaint
  • B. Inspection Results
  • C. Quality Task
  • D. Usage Decision

Answer: B,D


NEW QUESTION # 54
What are the different statuses of Quality Inspection on SAP Business Network? Note: There are 3 correct answers to this question.

  • A. Aligned
  • B. Assigned
  • C. Reviewed
  • D. Submitted
  • E. Pending

Answer: C,D,E


NEW QUESTION # 55
Under the subcontracting (backflush) scenario, which transaction triggers consumption of components in the buyer's ERP?

  • A. Component inventory
  • B. Update Inventory
  • C. Create ASN for finished goods
  • D. Post Goods Receipt

Answer: D


NEW QUESTION # 56
Which of the following transaction rules can the buyer enable during Scheduling Agreement configuration? Note: There are 3 correct answers to this question.

  • A. Allow suppliers to update Scheduling Agreements.
  • B. Allow suppliers to use both JIT type and Forecast type releases for shipping.
  • C. Allow suppliers to send order confirmations for Scheduling Agreements and Scheduling Agreement releases.
  • D. Allow suppliers to use only Forecast for shipping.
  • E. Allow suppliers to use only JIT for shipping.

Answer: B,C,D


NEW QUESTION # 57
Where would a user maintain cross-reference configuration parameters during Purchase Order Collaboration setup?

  • A. Default Transaction Rules on SAP Business Network (AN)
  • B. SAP Project Reference Object (SPRO)
  • C. Integrated Business Planning (IBP)
  • D. SAP Integration Suite Managed Gateway

Answer: A


NEW QUESTION # 58
Which documents are specific only to the subcontracting process?
Note: There are 2 correct answers to this question.

  • A. ERS Invoice
  • B. Subcontracting purchase order
  • C. Goods receipt
  • D. Component receipt

Answer: B,D


NEW QUESTION # 59
When does the buyer create a Quality Notification in the buyer-initiated model?

  • A. When there is a defect in the purchase order
  • B. When there is a defect in order confirmation
  • C. When there is a defect in the product
  • D. When there is a defect in the ASN

Answer: C


NEW QUESTION # 60
What level can supplier managed inventory business transaction rules be set to? Note: There are 2 correct answers to this question.

  • A. Country level
  • B. Buyer group level
  • C. Supplier level
  • D. Supplier group level

Answer: C,D


NEW QUESTION # 61
Which processes apply to component consumption in the subcontracting process?
Note: There are 2 correct answers to this question.

  • A. In real-time, the supplier needs to send a consumption report after the components have been used.
  • B. In backflush, the supplier needs to send a consumption report after the components have been used.
  • C. In backflush, the contract manufacturer does NOT need to report on the consumption of the components.
  • D. In real-time, the contract manufacturer does NOT need to report on the consumption of the components.

Answer: A,C


NEW QUESTION # 62
Which are key features of Multi-Tier Collaboration?
Note: There are 2 correct answers to this question.

  • A. Suppliers can provide manufacturing data to their buyers.
  • B. Suppliers can send a Purchase Order on behalf of the buyer.
  • C. Multiple suppliers and logistics providers can be a part of the Multi-Tier order.
  • D. Copy Suppliers can have visibility to Purchase Orders, Order Confirmations, and Advance Ship Notices.

Answer: C,D


NEW QUESTION # 63
What are the benefits of SAP Business Network Supply Chain Collaboration?
Note: There are 3 correct answers to this question.

  • A. Increase control
  • B. Reduce cost
  • C. Enhance end-to-end visibility
  • D. Increase inventory levels
  • E. Increase lead time

Answer: A,B,C


NEW QUESTION # 64
When a supplier creates a ship notice on SAP Business Network for a Scheduling Agreement release, which document is created in the buyer ERP?

  • A. Scheduling Agreement movement
  • B. Confirmation for Scheduling Agreement
  • C. Consignment movement
  • D. Inbound delivery

Answer: D


NEW QUESTION # 65
Which documents are part of SAP Ariba Purchase Order Collaboration? Note: There are 3 correct answers to this question.

  • A. Order Confirmation
  • B. Forecast Commit
  • C. Advance Ship Notice
  • D. Goods Receipt
  • E. Quality Inspection

Answer: A,B,C


NEW QUESTION # 66
What are the options available when suppliers create an Order Confirmation in SAP Business Network?
Note: There are 3 correct answers to this question.

  • A. Deliver Line Item
  • B. Approve Entire Order
  • C. Update Line Items
  • D. Confirm Entire Order
  • E. Reject Entire Order

Answer: C,D,E