NEW QUESTION 205
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is $30 per hour. Determine total cost and unit cost for a lot of 500.

  • A. Total Cost: $1455.00 & Unit cost: $2.90
  • B. Total Cost: $1400.00 & Unit cost: $2.80
  • C. Total Cost: $1440.00 & Unit cost: $2.60
  • D. Total Cost: $1450.00 & Unit cost: $2.90

Answer: D

 

NEW QUESTION 206
What is needed for items and is associated with master production scheduling?

  • A. Supply management
  • B. Demand management
  • C. Chain management
  • D. Product management

Answer: B

 

NEW QUESTION 207
The art charged by a carrier will also vary with the commodity shipped and will depend upon the following:

  • A. Density
  • B. All of these
  • C. Perishability
  • D. Value

Answer: B

 

NEW QUESTION 208
What is the reason for using the sample inspection?

  • A. human error is estimated to be as high as 20% when performing long-term repetitive testing
  • B. testing the product is destructive
  • C. All of the above
  • D. there is not enough time to give 100% inspection to a batch of product

Answer: C

 

NEW QUESTION 209
Which of eth following is NOT the source of waste in the design of the manufacturing system?

  • A. Movement
  • B. Process
  • C. Methods
  • D. Environment

Answer: D

 

NEW QUESTION 210
The formula for the seasonal demand is:

  • A. Seasonal demand = (seasonal index) * (deseasonalized demand)
  • B. Seasonal demand = (seasonal index) - (deseasonalized demand)
  • C. Seasonal demand = (seasonal index) / (deseasonalized demand)
  • D. Seasonal demand = (seasonal index) + (seasonalized demand)

Answer: A

 

NEW QUESTION 211
What is the updated forecast, utilizing exponential smoothing, given the following data?
Old Forecast = 100, actual demand = 80, alpha = 0.2, tracking signal = 0.9

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B

 

NEW QUESTION 212
Which of the following is NOT the method of forecasting?

  • A. intrinsic
  • B. qualitative
  • C. extrinsic
  • D. quantitative

Answer: D

 

NEW QUESTION 213
Which file contains a list of the single-level components and quantities needed to assemble a parent?

  • A. routing file
  • B. product structure file
  • C. master file
  • D. work center master file

Answer: B

 

NEW QUESTION 214
Metrics:

  • A. Direct a course of action
  • B. Communicate expectations and motivate people
  • C. Identify problems
  • D. All o0f these

Answer: D

 

NEW QUESTION 215
The flow of work centers must be planned to meet delivery dates which means production activity control must do the following:

  • A. Schedule start and completion dates for each shop order at each work center so the scheduled completion date of the order can be met. This sill involves a planner in developing a load profile for the work centers.
  • B. None of these
  • C. Both of these
  • D. Ensure that the required materials, tooling, personnel and information are available to manufacture the components when needed.

Answer: C

 

NEW QUESTION 216
Which of the following is an artificial grouping of components for planning purposes?

  • A. Indented bill
  • B. Summarized parts list
  • C. Single-level bill
  • D. Planning bill

Answer: D

 

NEW QUESTION 217
A simple system that signals the need for more products is known as:

  • A. Lot-for-more system
  • B. Manifesto system
  • C. Kanban system
  • D. Demanding system

Answer: C

 

NEW QUESTION 218
A term closely related to capacity required is planned work assigned to a facility for a par.

  • A. Load
  • B. Capacity available
  • C. Output
  • D. Target capacity

Answer: A

 

NEW QUESTION 219
Goods are not made continuously as in a flow system but are made at intervals in lots or batches in:

  • A. Inflexible manufacturing
  • B. Discrete manufacturing
  • C. Intermittent manufacturing
  • D. Fixed manufacturing

Answer: C

 

NEW QUESTION 220
Which of the following criteria is used to judge MPS?

  • A. All of these
  • B. Customer service
  • C. Resource use
  • D. Cost

Answer: A

 

NEW QUESTION 221
Using the , the quantity on hand of a particular item is determined at specified, fixed-time intervals and an order is placed.

  • A. Formal technical reviews
  • B. Walkthroughs
  • C. Periodic review system
  • D. Quality control

Answer: C

 

NEW QUESTION 222
Benefit/s of supply chain simulation is/are:

  • A. All of these
  • B. To be able to capture system dynamics: using probability distribution, user can model unexpected events in certain areas and understand the impact of these events on the supply chain
  • C. To help understand the overall supply chain processes and characteristics by graphics/animation
  • D. To minimize the risk of changes in planning process: by what-if simulation, user can test various alternatives before changing plan.

Answer: A

 

NEW QUESTION 223
objectives.

  • A. People
  • B. Processes
  • C. Projects
  • D. Products

Answer: B

 

NEW QUESTION 224
......