
100% PASS RATE APICS Certification CPIM Certified Exam DUMP with 590 Questions
Updates For the Latest CPIM Free Exam Study Guide!
NEW QUESTION 205
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is $30 per hour. Determine total cost and unit cost for a lot of 500.
- A. Total Cost: $1455.00 & Unit cost: $2.90
- B. Total Cost: $1400.00 & Unit cost: $2.80
- C. Total Cost: $1440.00 & Unit cost: $2.60
- D. Total Cost: $1450.00 & Unit cost: $2.90
Answer: D
NEW QUESTION 206
What is needed for items and is associated with master production scheduling?
- A. Supply management
- B. Demand management
- C. Chain management
- D. Product management
Answer: B
NEW QUESTION 207
The art charged by a carrier will also vary with the commodity shipped and will depend upon the following:
- A. Density
- B. All of these
- C. Perishability
- D. Value
Answer: B
NEW QUESTION 208
What is the reason for using the sample inspection?
- A. human error is estimated to be as high as 20% when performing long-term repetitive testing
- B. testing the product is destructive
- C. All of the above
- D. there is not enough time to give 100% inspection to a batch of product
Answer: C
NEW QUESTION 209
Which of eth following is NOT the source of waste in the design of the manufacturing system?
- A. Movement
- B. Process
- C. Methods
- D. Environment
Answer: D
NEW QUESTION 210
The formula for the seasonal demand is:
- A. Seasonal demand = (seasonal index) * (deseasonalized demand)
- B. Seasonal demand = (seasonal index) - (deseasonalized demand)
- C. Seasonal demand = (seasonal index) / (deseasonalized demand)
- D. Seasonal demand = (seasonal index) + (seasonalized demand)
Answer: A
NEW QUESTION 211
What is the updated forecast, utilizing exponential smoothing, given the following data?
Old Forecast = 100, actual demand = 80, alpha = 0.2, tracking signal = 0.9
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
NEW QUESTION 212
Which of the following is NOT the method of forecasting?
- A. intrinsic
- B. qualitative
- C. extrinsic
- D. quantitative
Answer: D
NEW QUESTION 213
Which file contains a list of the single-level components and quantities needed to assemble a parent?
- A. routing file
- B. product structure file
- C. master file
- D. work center master file
Answer: B
NEW QUESTION 214
Metrics:
- A. Direct a course of action
- B. Communicate expectations and motivate people
- C. Identify problems
- D. All o0f these
Answer: D
NEW QUESTION 215
The flow of work centers must be planned to meet delivery dates which means production activity control must do the following:
- A. Schedule start and completion dates for each shop order at each work center so the scheduled completion date of the order can be met. This sill involves a planner in developing a load profile for the work centers.
- B. None of these
- C. Both of these
- D. Ensure that the required materials, tooling, personnel and information are available to manufacture the components when needed.
Answer: C
NEW QUESTION 216
Which of the following is an artificial grouping of components for planning purposes?
- A. Indented bill
- B. Summarized parts list
- C. Single-level bill
- D. Planning bill
Answer: D
NEW QUESTION 217
A simple system that signals the need for more products is known as:
- A. Lot-for-more system
- B. Manifesto system
- C. Kanban system
- D. Demanding system
Answer: C
NEW QUESTION 218
A term closely related to capacity required is planned work assigned to a facility for a par.
- A. Load
- B. Capacity available
- C. Output
- D. Target capacity
Answer: A
NEW QUESTION 219
Goods are not made continuously as in a flow system but are made at intervals in lots or batches in:
- A. Inflexible manufacturing
- B. Discrete manufacturing
- C. Intermittent manufacturing
- D. Fixed manufacturing
Answer: C
NEW QUESTION 220
Which of the following criteria is used to judge MPS?
- A. All of these
- B. Customer service
- C. Resource use
- D. Cost
Answer: A
NEW QUESTION 221
Using the , the quantity on hand of a particular item is determined at specified, fixed-time intervals and an order is placed.
- A. Formal technical reviews
- B. Walkthroughs
- C. Periodic review system
- D. Quality control
Answer: C
NEW QUESTION 222
Benefit/s of supply chain simulation is/are:
- A. All of these
- B. To be able to capture system dynamics: using probability distribution, user can model unexpected events in certain areas and understand the impact of these events on the supply chain
- C. To help understand the overall supply chain processes and characteristics by graphics/animation
- D. To minimize the risk of changes in planning process: by what-if simulation, user can test various alternatives before changing plan.
Answer: A
NEW QUESTION 223
objectives.
- A. People
- B. Processes
- C. Projects
- D. Products
Answer: B
NEW QUESTION 224
......
Best CPIM Exam Preparation Material with New Dumps Questions https://www.passcollection.com/CPIM_real-exams.html
Fast Exam Updates CPIM dumps with PDF Test Engine Practice https://drive.google.com/open?id=13eUmsKtO-fcxL97OmJUTgWw9sJQIemqh

